Construction of Flood Mitigation Structure23DC0093

Construction of Flood Mitigation Structure along San Juan River, Tanauan - Sto. Tomas, Batangas

Construction of Flood Mitigation Structure along San Juan River, Tanauan - Sto. Tomas, Batangas is a DPWH-tracked public work in CITY OF TANAUAN (BATANGAS), BATANGAS, Region IV-A. Reported contract value: ₱96,499,284.50. Status: Reported complete (DPWH). Contractor on record: NDA BUILDERS AND DEVELOPERS / REVERE CONST & SUPPLY CORP FORMERLY. Figures trace to sumbong.

CITY OF TANAUAN (BATANGAS), BATANGAS, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Probable match · score 95%

UACS
18001
Amount
₱100,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structures Along San Juan River - Phase 5, Tanauan - Sto. Tomas, Batangas
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Batangas 3rd District Engineering Office · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

1 projects · ₱96.5M total · 1 flags

4. Implementation

Contract Amount

₱96,499,284.50

Progress

Reported complete (DPWH)

Start Date

March 17, 2023

Target End

February 9, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.