Buildings and Facilities22K00237

CONSTRUCTION OF MULTI-PURPOSE FACILITY, BRGY. LIMBAC, POONA BAYABAO, LANAO DEL SUR

CONSTRUCTION OF MULTI-PURPOSE FACILITY, BRGY. LIMBAC, POONA BAYABAO, LANAO DEL SUR is a DPWH-tracked public work in Region X, Region X. Reported contract value: ₱5,848,942.86. Status: Reported complete (DPWH). Contractor on record: FKB BUILDERS AND ENT. Figures trace to dpwh.

Region X, Region X
Region: Region X

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2022 GAA. DBM GAA FY2022

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱5,848,942.86

Progress

Reported complete (DPWH)

Start Date

October 10, 2022

Target End

March 8, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.