Rehabilitation / Major Repair of Drainage Structure25OE0103

Rehabilitation of Drainage Structure, Phase 5, Zone 41-57, Manila City

Rehabilitation of Drainage Structure, Phase 5, Zone 41-57, Manila City is a DPWH-tracked public work in CITY OF MANILA (METROPOLITAN MANILA), CITY OF MANILA, National Capital Region. Reported contract value: ₱4,798,989.63. Status: Reported complete (DPWH). Contractor on record: LE BRON CONST. Figures trace to sumbong.

CITY OF MANILA (METROPOLITAN MANILA), CITY OF MANILA, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱15,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Estero de Sunog Apog, Barangay 172, Manila City
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-25-0008064

₱316,000,000.00 · FY2025

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-NCR-25-0006072

₱2,775,000.00 · FY2025

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-NCR-25-0006073

₱279,000.00 · FY2025

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

249 projects · ₱16.0B total · 11 flags

4. Implementation

Contract Amount

₱4,798,989.63

Progress

Reported complete (DPWH)

Start Date

February 17, 2025

Target End

May 30, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.