Roads23CE0122

ROAD CONSTRUCTION OF TALUGTUG - UMINGAN ROAD WITH BARREL BOX CULVERT IN TALUGTUG, NUEVA ECIJA (PHASE 2)

ROAD CONSTRUCTION OF TALUGTUG - UMINGAN ROAD WITH BARREL BOX CULVERT IN TALUGTUG, NUEVA ECIJA (PHASE 2) is a DPWH-tracked public work in Nueva Ecija 1st DEO, Region III. Reported contract value: ₱19,402,024.78. Status: Reported complete (DPWH). Contractor on record: ADROIT EJD CONST CORP FORMERLY: ADROIT CONST. Figures trace to dpwh.

Nueva Ecija 1st DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structures along Rio Chico River, Brgy. Bacayao, Guimba, Nueva Ecija (Phase 2)
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Nueva Ecija 1st DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

232 projects · ₱2.4B total · 1 flags

4. Implementation

Contract Amount

₱19,402,024.78

Progress

Reported complete (DPWH)

Start Date

March 28, 2023

Target End

September 23, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.