Water Provision and Storage22FO0114

CONSTRUCTION OF WATER SYSTEM (LEVEL II) BRGYS. BASICAO INTERIOR, STO. CRISTO, SUKIP, ORINGON, MUNICIPALITY OF PIODURAN, ALBAY

CONSTRUCTION OF WATER SYSTEM (LEVEL II) BRGYS. BASICAO INTERIOR, STO. CRISTO, SUKIP, ORINGON, MUNICIPALITY OF PIODURAN, ALBAY is a DPWH-tracked public work in Albay 3rd DEO, Region V. Reported contract value: ₱23,759,613.24. Status: Reported complete (DPWH). Contractor on record: FGO CONST. Figures trace to dpwh.

Albay 3rd DEO, Region V
Region: Region V

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Muladbucad Flood Control Dike in Muladbucad, Guinobatan, Albay
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Albay 3rd DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

D

12 projects · ₱195.8M total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO AIRPORTS (KALSADA TUNGO SA PALIPARAN, RILES AT DAUNGAN PROGRAM-KATUPARAN)-JCT. DM (TABON-TABON)-MARIAWA-HOMAPON-MASLOG-LAMBA-PURO ROAD LEADING TO BICOL INTERNATI

Region V, Region V

2025₱46.9M
Past target date (DPWH On-Going)
No sat.

SIPAG: CONSTRUCTION OF MABINIT-LIDONG ALTERNATE ROAD, PHASE 2, LEGAZPI CITY

Albay 2nd DEO, Region V

2022₱29.4M
Reported complete (DPWH)
No sat.

BASIC INFRASTRUCTURE PROGRAM: CONSTRUCTION OF WATER SYSTEM LEVEL II IN BRGY. ANISLAG, BRGY. KIWALO, BRGY. MAYON, BRGY. NAMANTAO, AND BRGY. VILLAHERMOSA, DARAGA, ALBAY

Albay 2nd DEO, Region V

2022₱23.7M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP)-CONSTRUCTION/REHABILITATION OF WATER SUPPLY/SEPTAGE AND SEWERAGE/RAIN WATER COLLECTORS-WATER SUPPLY SYSTEM-CONSTRUCTION OF SOLAR WATER SYSTEM LEVEL II, NABUA, CAMARINES SUR, LOURDES YOUNG, LA PURISIMA AND LA

Region V, Region V

2023₱14.5M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM(CSSP)-CONSTRUCTION/REHABILITATION OF WATER SUPPLY/SEPTAGE AND SEWERAGE/RAIN WATER COLLECTORS-WATER SUPPLY SYSTEM-CONSTRUCTION OF SOLAR WATER SYSTEM LEVEL II, TINAMBAC, CAMARINES SUR, LA MEDALLA, BINALAY AND PAG-ASA,

Region V, Region V

2023₱14.0M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP)-BASIC INFRASTRUCTURE PROGRAM(BIP)-PUBLIC WATER SUPPLY SYSTEM (LEVEL II OR III)-CONSTRUCTION OF VARIOUS SOLAR WATER SYSTEM LEVEL II IN THE MUNICIPALITY OF GOA, CAMARINES SUR, BRGY. MAYSALAY AND BRGY. LAMON, GO

Region V, Region V

2023₱9.9M
Reported complete (DPWH)
View all 12 projects →

4. Implementation

Contract Amount

₱23,759,613.24

Progress

Reported complete (DPWH)

Start Date

August 15, 2022

Target End

April 11, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.