Construction of Flood Mitigation Facility24BC0077

Construction of Lucban Flood Control along Abulug River, Abulug, Cagayan

Construction of Lucban Flood Control along Abulug River, Abulug, Cagayan is a DPWH-tracked public work in ABULUG (CAGAYAN), CAGAYAN, Region II. Reported contract value: ₱24,500,000.00. Status: Reported complete (DPWH). Contractor on record: J G YACAS CONST SUPPLY AND EQUIPMENT RENTAL. Figures trace to sumbong.

ABULUG (CAGAYAN), CAGAYAN, Region II
Region: Region II

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱25,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Lucban Flood Control along Abulug River, Abulug, Cagayan
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROII-24-0010607

₱1,860,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROII-24-0000878

₱1,207,156.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROII-24-0005893

₱783,512.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROII-24-0006344

₱15,000,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROII-24-0010618

₱172,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROII-24-0000883

₱149,442.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROII-24-0000879

₱102,960.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROII-24-0001122

₱227,030.00 · FY2024

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

110 projects · ₱1.7B total · 2 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM- BASIC INFRASTRUCTURE PROGRAM (BIP)- MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES- CONSTRUCTION OF MULTI-PURPOSE BUILDING (GOVERNMENT CENTER PACKAGE 4), LIBERTAD, ABULUG, CAGAYAN

Cagayan 2nd DEO, Region II

2024₱99.0M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF DUGO FLOOD CONTROL ALONG ABULU

Cagayan 2nd DEO, Region II

2025₱96.3M
Past target date (DPWH On-Going)

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS: CONSTRUCTION OF LIBERTAD FLOOD CONTROL STRUCTUR

Cagayan 2nd DEO, Region II

2025₱96.3M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF DUGO FLOOD CONTROL CONTROL STR

Cagayan 2nd DEO, Region II

2025₱96.3M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM- CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONSTRUCTION OF ABULUG RIVER REVETMENT 9 ALO

Cagayan 2nd DEO, Region II

2025₱96.3M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM- CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS- CONSTRUCTION OF CAGAYAN RIVER REVETMENT 5 AL

Cagayan 2nd DEO, Region II

2025₱96.3M
Past target date (DPWH On-Going)
View all 110 projects →

4. Implementation

Contract Amount

₱24,500,000.00

Progress

Reported complete (DPWH)

Start Date

March 4, 2024

Target End

August 11, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.