Buildings and Facilities21HJ0116

CONSTRUCTION/COMPLETION OF 1 UNIT 1 STOREY 1 CLASSROOM SCHOOL BUILDING AT PULA ES, CANLAON CITY, NEGROS ORIENTAL

CONSTRUCTION/COMPLETION OF 1 UNIT 1 STOREY 1 CLASSROOM SCHOOL BUILDING AT PULA ES, CANLAON CITY, NEGROS ORIENTAL is a DPWH-tracked public work in Negros Oriental 1st DEO, Negros Island Region. Reported contract value: ₱1,619,000.00. Status: Reported complete (DPWH). Contractor on record: ALOJA BUILDERS AND REALTY. Figures trace to dpwh.

Negros Oriental 1st DEO, Negros Island Region
Region: Negros Island Region

Money Trail

1. Appropriation

Probable match · score 85%

UACS
18001
Amount
₱1,500,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control along Mabigo River Canlaon City, Negros Oriental
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Negros Oriental 1st DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

Probable match · 94%

Construction of Box Culvert

₱1,640,255.00 · ALOJA BUILDERS AND REALTY

Contractor

172 projects · ₱1.1B total · 0 flags

Other projects by this contractor

No sat.

LOCAL PROGRAM - LOCAL INFRASTRUCTURE PROGRAM - LOCAL ROADS AND BRIDGES - LOCAL ROADS - CONCRETING OF ROADS AT SITIO CANTUGOP, NAPO TO BRGY. PUTLONGCAM, ALICIA, BOHOL ST. 0+000.00 - STA.3+202.90 WITH EXCEPTION - SECTION 1; STA. 2+065.00 - STA. 2+365 - SECT

Bohol 3rd DEO, Region VII

2020₱49.5M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM- BASIC INFRASTRUCTURE PROGRAM (BIP) ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION (CONCRETING) OF ROAD AT BRGY. WEST CANAYAON TO BRGY. CAL

Bohol 3rd DEO, Region VII

2023₱39.6M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF BRGY. BINLOD BARANGAY ROAD, ARGAO, CEBU

Cebu 2nd DEO, Region VII

2025₱39.5M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM BASIC INFRASTRUCTURE PROGRAM BIP - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES CONSTRUCTION (CONCRETING) OF ROAD AT BARANGAY BUGANG SUR TO BARANGAY C

Bohol 3rd DEO, Region VII

2023₱34.6M
Reported complete (DPWH)
No sat.

CONVERGENCE & SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROADS, VALENCIA, BOHOL, SEC. 1: STA. 0+000.00 - STA

Bohol 3rd DEO, Region VII

2024₱34.6M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM - REHAB./RECONST. OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDES - SECONDARY ROADS, TAGB. EAST ROAD (TAGB.-JAGNA), JAGNA, BOHOL K0193+620.00 - K0193+6

Bohol 3rd DEO, Region VII

2021₱28.1M
Reported complete (DPWH)
View all 172 projects →

4. Implementation

Contract Amount

₱1,619,000.00

Progress

Reported complete (DPWH)

Start Date

October 7, 2021

Target End

December 31, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.