Roads25F00380

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF BY-PASS AND DIVERSION ROADS-TAGKAWAYAN-LABO DIVERSION ROAD (LABO SECTION), CAMARINES NORTE, LABO, CAMARINES NORTE

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF BY-PASS AND DIVERSION ROADS-TAGKAWAYAN-LABO DIVERSION ROAD (LABO SECTION), CAMARINES NORTE, LABO, CAMARINES NORTE is a DPWH-tracked public work in Region V, Region V. Reported contract value: ₱87,298,601.20. Status: Past target date (DPWH On-Going). Contractor on record: WAYCON BUILDERS AND CONST SUPPLY CORP FOR:WAYCON BUILDERS. Figures trace to dpwh.

Region V, Region V
Region: Region V

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

474 projects · ₱22.2B total · 0 flags

4. Implementation

Contract Amount

₱87,298,601.20

Progress

Past target date (DPWH On-Going)

Start Date

May 29, 2025

Target End

March 1, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.