Buildings and Facilities16DP0052

REHABILITATION AND IMPROVEMENT OF MEDICAL WARDS (LEFT WING), SAN PABLO CITY GENERAL HOSPITAL, SAN PABLO CITY, LAGUNA

REHABILITATION AND IMPROVEMENT OF MEDICAL WARDS (LEFT WING), SAN PABLO CITY GENERAL HOSPITAL, SAN PABLO CITY, LAGUNA is a DPWH-tracked public work in Laguna 3rd DEO, Region IV-A. Reported contract value: ₱3,931,960.82. Status: Reported complete (DPWH). Contractor on record: CHRISTIAN LEY CONST. Figures trace to dpwh.

Laguna 3rd DEO, Region IV-A
Region: Region IV-A

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱19,500,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction / Maintenance of Flood Mitigation Structures and Drainage Systems at Magampon River Passing thru Poblacion Maharlika Highway, San Pablo City Section, Laguna
GAA fiscal year
FY2016
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIX-16-0030618

₱655,280.00 · FY2016

Released to Zamboanga Sibugay National High School (Pangi Re (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱3,931,960.82

Progress

Reported complete (DPWH)

Start Date

December 1, 2016

Target End

March 30, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.