Buildings and Facilities15LF0087

CONST. OF MULTI-PURPOSE BUILDING, BARANGAY SALINGCOMOT, BAGANGA, DAVAO ORIENTAL

CONST. OF MULTI-PURPOSE BUILDING, BARANGAY SALINGCOMOT, BAGANGA, DAVAO ORIENTAL is a DPWH-tracked public work in Davao Oriental 1st DEO, Region XI. Reported contract value: ₱1,946,377.09. Status: Reported complete (DPWH). Contractor on record: LLM UNIFIED BUILDERS. Figures trace to dpwh.

Davao Oriental 1st DEO, Region XI
Region: Region XI

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

GAA FY2016 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱1,946,377.09

Progress

Reported complete (DPWH)

Start Date

February 9, 2016

Target End

April 8, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.