GAA 2025 OO-125CN0020

REPLACEMENT OF PERMANENT WEAK BRIDGES LIPIT BR. (B03016LZ) ALONG BALER-CASIGURAN RD (BALER-DINADIAWAN)

REPLACEMENT OF PERMANENT WEAK BRIDGES LIPIT BR. (B03016LZ) ALONG BALER-CASIGURAN RD (BALER-DINADIAWAN) is a DPWH-tracked public work in Aurora DEO, Region III. Reported contract value: ₱45,487,776.28. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: R N G M CONST CORP FORMERLY: R N G M CONST. Figures trace to dpwh.

Aurora DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Possible match · score 62%

UACS
18001
Amount
₱47,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Lipit Br. (B03016LZ) along Baler-Casiguran Rd (Baler-Dinadiawan)
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Aurora DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

4. Implementation

Contract Amount

₱45,487,776.28

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

February 18, 2025

Target End

November 14, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.