Construction of Flood Mitigation Structure22IH0047

Construction of Flood Control Structure along Brgy. Colab-og (Colab-og Bridge), Victoria, Northern Samar

Construction of Flood Control Structure along Brgy. Colab-og (Colab-og Bridge), Victoria, Northern Samar is a DPWH-tracked public work in VICTORIA (NORTHERN SAMAR), NORTHERN SAMAR, Region VIII. Reported contract value: ₱48,044,665.17. Status: Reported complete (DPWH). Contractor on record: RNMK CONST SUPPLY AND DEVELOPMENT CORP FOR: RNMK CONST & DEV'T / CDU CONST. Figures trace to sumbong.

VICTORIA (NORTHERN SAMAR), NORTHERN SAMAR, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Brgy. Colab-og (Colab-og Bridge), Victoria, Northern Samar
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003182

₱192,636,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-22-0013001

₱27,584.00 · FY2022

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

4. Implementation

Contract Amount

₱48,044,665.17

Progress

Reported complete (DPWH)

Start Date

February 21, 2022

Target End

October 24, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.