Construction of Flood Mitigation Structure23AB0097

Construction of Flood Control Structure along San Lorenzo Creek, Both Bank, Brgy. San Lorenzo, San Nicolas, Ilocos Norte

Construction of Flood Control Structure along San Lorenzo Creek, Both Bank, Brgy. San Lorenzo, San Nicolas, Ilocos Norte is a DPWH-tracked public work in SAN NICOLAS (ILOCOS NORTE), ILOCOS NORTE, Region I. Reported contract value: ₱33,270,657.32. Status: Reported complete (DPWH). Contractor on record: BJMJB CONST & SUPPLY. Figures trace to sumbong.

SAN NICOLAS (ILOCOS NORTE), ILOCOS NORTE, Region I
Region: Region I

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱35,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along San Lorenzo Creek, Both Bank, Brgy. San Lorenzo, San Nicolas, Ilocos Norte
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Ilocos Norte 2nd District Engineering Office · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱33,270,657.32

Progress

Reported complete (DPWH)

Start Date

April 24, 2023

Target End

December 14, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.