Roads22K00012

CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, ILIGAN CITY CIRCUMFERENTIAL ROAD EXTENSION TO JCT. STA. FELOMINA-BONBONON-DIGKILAAN-ROGONGON ROAD, PACKAGE 4, LANAO DEL NORTE

CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, ILIGAN CITY CIRCUMFERENTIAL ROAD EXTENSION TO JCT. STA. FELOMINA-BONBONON-DIGKILAAN-ROGONGON ROAD, PACKAGE 4, LANAO DEL NORTE is a DPWH-tracked public work in Region X, Region X. Reported contract value: ₱101,325,000.00. Status: Reported complete (DPWH). Contractor on record: ME 3 CONST 31364. Figures trace to dpwh.

Region X, Region X
Region: Region X

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱101,325,000.00

Progress

Reported complete (DPWH)

Start Date

March 30, 2022

Target End

June 25, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.