Buildings and Facilities23FO0070

BIP - EVACUATION CENTERS/ QUARANTINE FACILITIES/PUBLIC HEALTH FACILITIES - CONSTRUCTION OF MULTI-PURPOSE FACILITY (BIRTHING FACILITY), MAYON UNIT BARANGAYS, GUINOBATAN, ALBAY

BIP - EVACUATION CENTERS/ QUARANTINE FACILITIES/PUBLIC HEALTH FACILITIES - CONSTRUCTION OF MULTI-PURPOSE FACILITY (BIRTHING FACILITY), MAYON UNIT BARANGAYS, GUINOBATAN, ALBAY is a DPWH-tracked public work in Albay 3rd DEO, Region V. Reported contract value: ₱4,733,761.36. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: IMS CONST. Figures trace to dpwh.

Albay 3rd DEO, Region V
Region: Region V

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Muladbucad Flood Control Phase II, Guinobatan, Albay
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Albay 3rd DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

29 projects · ₱194.0M total · 0 flags

Other projects by this contractor

No sat.

CONSTRUCTION OF TWO (2) UNITS THREE (3) STOREY REGULAR WORKSHOP, ICT, AND SCIENCE LABORATORY BUILDING SALVACION HIGH SCHOOL, SALVACION, BATO, CAMARINES SUR

Camarines Sur 5th DEO, Region V

2018₱28.8M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF CONCRETE ROAD-POB-MOROCBOROCAN-GUINHADAP ROAD LEADING TO SAN MIGUEL ISLAND DIVE SITE & LIGHT HOUSE, HALEA NATURE PARK, PABORITO ROCK GARDEN, DANAO BEACH, LAPUS LAPUS BLUE LAGOON, TRES MARIAS ISLAND, GUINLATAYAN BIRD SANCTUARY,MONREAL, MAS.

Masbate 1st DEO, Region V

2019₱28.5M
Reported complete (DPWH)
No sat.

CSSP: CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM - TRIP) - CAMALIG TOURISM CIRCUIT LEADING TO SUMLANG LAKE, QUITINDAY HILLS, QUITUINAN JAPANESE TUNNEL AND HOYOP-HOYOPAN CAVE SITE

Albay 2nd DEO, Region V

2024₱14.3M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF CONCRETE ROAD - CONCRETING OF ROAD IN BARANGAY BUENOS AIRES TO BUENA SUERTE.

Masbate 1st DEO, Region V

2019₱14.3M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP) - CONSTRUCTION/ REHABILITATION OF WATER SUPPLY/ SEPTAGE AND SEWERAGE/ RAIN WATER COLLECTORS - WATER SUPPLY - CONSTRUCTION OF SOLAR WATER SYSTEM, MUNICIPALITY OF SAN JACINTO, PROVINCE OF MASBATE.

Masbate 1st DEO, Region V

2023₱9.8M
Reported complete (DPWH)
No sat.

CSSP - CONSTRUCTION/ IMPROVEMENT OF ACCESS ROAD LEADING TO DECLARED TOURISM DESTINATIONS (TRIP) - POBLACION-MOROCBOROCAN-GUINHADAP ROAD LEADING TO SAN MIGUEL ISLAND DIVE SITE AND LIGHT HOUSE AND OTHER TOURISM AREAS, BRGY. GUINHADAP, MONREAL, MASBATE.

Masbate 1st DEO, Region V

2023₱9.8M
Reported complete (DPWH)
View all 29 projects →

4. Implementation

Contract Amount

₱4,733,761.36

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

July 17, 2023

Target End

January 12, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.