Construction of Slope Protection Structure22CI0095

Construction of reinforced concrete slope protection with steel sheet piles foundation along Abacan river, Sapalibutad, Angeles city, Pampanga

Construction of reinforced concrete slope protection with steel sheet piles foundation along Abacan river, Sapalibutad, Angeles city, Pampanga is a DPWH-tracked public work in ANGELES CITY (PAMPANGA), PAMPANGA, Region III. Reported contract value: ₱23,900,621.10. Status: Reported complete (DPWH). Contractor on record: THREE-IN-ONE CONST & TRADING. Figures trace to sumbong.

ANGELES CITY (PAMPANGA), PAMPANGA, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Gumain River, Cabangcalan Section, Barangay Cabangcalan, Floridablanca, Pampanga
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0001629

₱159,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIII-22-0012252

₱1,104,074.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIII-22-0002420

₱749,061.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002914

₱723,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIII-22-0004169

₱110,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIII-22-0002421

₱71,763.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIII-22-0005826

₱46,080.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIII-22-0010260

₱254,906.00 · FY2022

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱23,900,621.10

Progress

Reported complete (DPWH)

Start Date

March 24, 2022

Target End

September 11, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.