Bridges22G00105

CONSTRUCTION OF BRIDGE BARANGAY PUNAO TO SO. BANDERA, SAN CARLOS CITY, NEGROS OCCIDENTAL

CONSTRUCTION OF BRIDGE BARANGAY PUNAO TO SO. BANDERA, SAN CARLOS CITY, NEGROS OCCIDENTAL is a DPWH-tracked public work in Region VI, Region VI. Reported contract value: ₱4,949,999.25. Status: Reported complete (DPWH). Contractor on record: HUMMING BIRD CONST. Figures trace to dpwh.

Region VI, Region VI
Region: Region VI

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2022 GAA. DBM GAA FY2022

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

112 projects · ₱571.4M total · 0 flags

4. Implementation

Contract Amount

₱4,949,999.25

Progress

Reported complete (DPWH)

Start Date

March 29, 2022

Target End

September 24, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.