Roads18KJ0187

CONSTRUCTION OF MISSING LINKS/NEW ROADS, BONIFACIO-DON VICTORIANO ROAD (BUENAVISTA-MARA-MARA SECTION MISAMIS OCCIDENTAL

CONSTRUCTION OF MISSING LINKS/NEW ROADS, BONIFACIO-DON VICTORIANO ROAD (BUENAVISTA-MARA-MARA SECTION MISAMIS OCCIDENTAL is a DPWH-tracked public work in Misamis Occidental 2nd DEO, Region X. Reported contract value: ₱91,674,797.68. Status: Reported complete (DPWH). Contractor on record: MINDANAO ROCK. Figures trace to dpwh.

Misamis Occidental 2nd DEO, Region X
Region: Region X

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Clarin Drainage System, Including ROW, Clarin, Misamis Occidental
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-E-18-0018857

₱8,639,025.00 · FY2018

Released to Central Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱91,674,797.68

Progress

Reported complete (DPWH)

Start Date

May 21, 2018

Target End

October 22, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.