Buildings and Facilities19HE0099

COMPLETION OF MULTI-PURPOSE BUILDING, BRGY. POBLACION, SIBONGA, CEBU

COMPLETION OF MULTI-PURPOSE BUILDING, BRGY. POBLACION, SIBONGA, CEBU is a DPWH-tracked public work in Cebu 1st DEO, Region VII. Reported contract value: ₱1,950,000.00. Status: Reported complete (DPWH). Contractor on record: SOLIDCORE CONST. Figures trace to dpwh.

Cebu 1st DEO, Region VII
Region: Region VII

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱1,950,000.00

Progress

Reported complete (DPWH)

Start Date

August 1, 2019

Target End

October 19, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.