Buildings and Facilities18HF0126

CONSTRUCTION OF ONE (1) UNIT-THREE (3) STOREY, SIX (6) CL, DPWH-DEPED STD. SCHOOL BUILDING AT PARIL ELEMENTARY SCHOOL, BARILI, CEBU

CONSTRUCTION OF ONE (1) UNIT-THREE (3) STOREY, SIX (6) CL, DPWH-DEPED STD. SCHOOL BUILDING AT PARIL ELEMENTARY SCHOOL, BARILI, CEBU is a DPWH-tracked public work in Cebu 3rd DEO, Region VII. Reported contract value: ₱13,820,097.48. Status: Reported complete (DPWH). Contractor on record: SOLIDCORE CONST. Figures trace to dpwh.

Cebu 3rd DEO, Region VII
Region: Region VII

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Revetment (rubble conrete) at Sta. Ana River along Carcar-Barili Road/Barili-Mantayupan Road, Sta. 2+220 - Sta. 2+530, Brgy Poblacion, Barili, Cebu
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROIVB-18-0019685

₱622,420.00 · FY2018

Released to Mabini National High School (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

59 projects · ₱269.8M total · 0 flags

4. Implementation

Contract Amount

₱13,820,097.48

Progress

Reported complete (DPWH)

Start Date

July 3, 2018

Target End

December 14, 2018