DPWH projects in Cebu

7,454 DPWH public works projects are recorded in Cebu (Region Vii), with start dates from 2016 to 2025. Recorded contract values total about ₱160,459,583,910.58. 6,421 are recorded at 100% progress and 992 are flood control works. Figures are as recorded by DPWH; they are not findings.

Largest recorded projects

  1. Repair / Rehabilitation / Reconstruction of National Roads and Bridges, Flood Control, Other Public₱250,885,722.13
  2. Construction of Flood Mitigation Structure Along Tipolo River, Mandaue City, Cebu₱173,700,000.00
  3. Cssp: Bip - Multi-Purpose Buildings/ Facilities to Support Social Services -Construction (Completion) of Multi-Purpose Building, Eversley Childs Sanitarium and General Hospital, Mandaue City, Cebu₱163,319,888.00
  4. Construction of Flood Control Structure Along Cotcot River, Upstream, Liloan, Cebu₱149,847,604.40
  5. Construction of Severo M. Verallo Provinical Hospital Complex (Cebu Provincial Hospital), Taytayon, Bogo City, Cebu₱149,799,845.00
  6. Construction of Revetment Wall Structure Along Mananga River (Right Side), Sitio Bogo, Barangay Camp 4, Talisay City, Cebu₱148,500,000.00
  7. Construction of Revetment Wall Structure Along Mananga River (Left Side), Sitio Bogo, Barangay Camp 4, Talisay City, Cebu₱148,500,000.00
  8. Construction of Dike, Brgy. MontañEza-Brgy. Lombo, Malabuyoc, Cebu₱148,495,065.10
  9. Convergence and Special Support Program - Basic Infrastructure Program (Bip) - Flood Mitigation Structures Protecting Major/Strategic Public Buildings/Facilities - Construction of Flood Control Structure, Barangay Simala, Sibonga, Cebu₱148,430,000.00
  10. Convergence and Special Support Program, Basic Infrastructure Program (Bip), Flood Mitigation Structures Protecting Major/ Strategic Public Buildings/ Facilities, Construction of Seawall Protection Structure Along Santander-Barili-Toledo Road at Sitio Man₱145,530,000.00
  11. Convergence and Special Support Program, Basic Infrastucture Program (Bip), Flood Mitigation Structures Protecting Major/ Strategic Public Buildings/Facilities, Construction of Tubod River Flood Control, Barangay Tubod - Duguan, Dumanjug, Cebu (Phase 3)₱145,530,000.00
  12. Convergence and Special Support Program, Basic Infrastructure, Program (Bip), Access Roads and/Or Bridges From the National Roads Leading to Major/ Strategic Public Buildings/ Facilities, Construction of Brgy. Kantangkas- Brgy. Paculob Road, Dumanjug, Ce₱145,529,500.00
  13. Convergence and Special Support Program, Basic Infrastructure Program (Bip), Flood Mitigation Structures Protecting Major/ Strategic Public Buildings/ Facilities, Construction of Seawall Protection Structure Along Santander-Barili-Toledo Road at Sitio Lut₱145,529,000.00
  14. Convergence and Special Support Program, Basic Infrastructure Program (Bip), Flood Mitigation Structures Protecting Major/Strategic Public Buildings/Facilities, Construction of Revetment Wall at Brgy. Kanghalo (Downstream), Dumanjug, Cebu (Phase 3)₱145,529,000.00
  15. Organizational Outcome 2: Protect Lives and Properties Against Major Floods - Flood Management Program - Const/Rehab of Flood Mitigation Facilities W/in Major River Basins and Principal Rivers - Const of Dumlog River Flood Control Structure, Sibonga, Cebu₱144,750,000.00
  16. Construction of Flood Control Along Mananga River (Right Side) at Sitio Tigib, Barangay Lagtang, Talisay City, Cebu (Package 2)₱144,750,000.00
  17. Construction of Flood Control Along Mananga River (Left Side) at Sitio Tigib, Barangay Lagtang, Talisay City, Cebu (Package 4)₱144,750,000.00
  18. Construction of Flood Control Along Mananga River (Right Side) at Sitio Tigib, Barangay Lagtang, Talisay City, Cebu (Package 3)₱144,750,000.00
  19. Construction of Flood Control Along Mananga River (Left Side) at Sitio Tigib, Barangay Lagtang, Talisay City, Cebu (Package 3)₱144,750,000.00
  20. Asset Preservation - Rehabilitation/Reconstruction of Roads With Slips, Slope Collapse and Landslide - Cebu - Balamban Transcentral Highway - K0030+121 - K0030+195, K0032+243 - K0032+307, K0037+000 - K0037+600, K0038+095 - K0038+197, K0039+779 - K0039+922₱144,750,000.00
  21. Cssp: Sustainable Infrastructure Projects Alleviating Gaps (Sipag) - Access Roads and/Or Bridges From the National Road/S Leading to Major/Strategic Public Buildings/ Facilities - Const. of Road Leading to Roro Port Phase 1, Brgy. Poblacion, Cordova, Cebu₱144,750,000.00
  22. Cssp: Sipag - Flood Mitigation Structures Protecting Major/ Strategic Public Buildings/ Facilities - Construction of Flood Control Structure Along Jagobiao Creek, Barangay Casili, Phase 2, Mandaue City, Cebu₱144,750,000.00
  23. Construction of Flood Control Structure Along Polo River (Downstream Left Side), Alcantara, Cebu₱144,745,350.30
  24. Organizational Outcome 1: Ensure Safe and Reliable National Road System, Bridge Program, Replacement of Bridges (Temporary to Permanent), Manduyong Bridge Along Santander-Barili-Toledo Road - K0195 + 198 - K0195 + 220₱144,743,076.49
  25. Organizational Outcome 2: Protect Lives and Properties Against Major Floods - Flood Management Program - Const/Maint of Flood Mitigation Structures and Drainage Systems - Const of Flood Control Along Mananga River (Right Side) at Sitio Kawatan, Brgy Tabun₱144,731,000.00