Flood Control and Drainage20CC0167

CONSTRUCTION OF CONCRETE RIVER PROTECTION AT DALIG, STA. 04+038 - STA. 04+433, BALAGTAS, BULACAN

CONSTRUCTION OF CONCRETE RIVER PROTECTION AT DALIG, STA. 04+038 - STA. 04+433, BALAGTAS, BULACAN is a DPWH-tracked public work in Bulacan 1st DEO, Region III. Reported contract value: ₱49,499,999.74. Status: Reported complete (DPWH). Contractor on record: ORANI CONST AND SUPPLY CORP FORMERLY:ORANI BUILDERS. Figures trace to dpwh.

Bulacan 1st DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure Along Balagtas River, Brgy. Wawa, Balagtas, Bulacan
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Bulacan 1st DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

337 projects · ₱12.4B total · 0 flags

4. Implementation

Contract Amount

₱49,499,999.74

Progress

Reported complete (DPWH)

Start Date

November 26, 2020

Target End

January 31, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.