Flood Control and Drainage25IA0054

CONSTRUCTION OF ARIQUIN FLOOD CONTROL STRUCTURE ALONG BILIRAN CIRCUMFERENTIAL ROAD, PHASE I, CABUCGAYAN, BILIRAN

CONSTRUCTION OF ARIQUIN FLOOD CONTROL STRUCTURE ALONG BILIRAN CIRCUMFERENTIAL ROAD, PHASE I, CABUCGAYAN, BILIRAN is a DPWH-tracked public work in Biliran DEO, Region VIII. Reported contract value: ₱48,975,848.49. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: LCTING CONST AND DEVELOPMENT CORP FORMERLY: L C TING CONST. Figures trace to dpwh.

Biliran DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Probable match · score 96%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Ariquin Flood Control Structure along Biliran Circumferential Road, Phase I, Cabucgayan, Biliran
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Biliran DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

304 projects · ₱17.1B total · 2 flags

4. Implementation

Contract Amount

₱48,975,848.49

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

February 28, 2025

Target End

October 31, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.