Bridges18DD0067

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, BRIDGE PROGRAM, WIDENING OF PERMANENT BRIDGES, PUNLAAN BR. (B03116LZ) ALONG SAN JUAN - LAIYA RD., SAN JUAN, BATANGAS

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, BRIDGE PROGRAM, WIDENING OF PERMANENT BRIDGES, PUNLAAN BR. (B03116LZ) ALONG SAN JUAN - LAIYA RD., SAN JUAN, BATANGAS is a DPWH-tracked public work in Batangas 4th DEO, Region IV-A. Reported contract value: ₱11,760,000.00. Status: Reported complete (DPWH). Contractor on record: THREE W BUILDERS INC. Figures trace to dpwh.

Batangas 4th DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Slope Protection/Revetment at Lawaye Br. Along San Juan - Laiya Rd, San Juan, Batangas
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-B-18-0016454

₱15,000,000.00 · FY2018

Released to Regional Office - IVA (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

416 projects · ₱20.3B total · 2 flags

4. Implementation

Contract Amount

₱11,760,000.00

Progress

Reported complete (DPWH)

Start Date

February 13, 2018

Target End

October 31, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.