Buildings and Facilities16OF0126

COMPLETION OF SENIOR HIGH SCHOOL BUILDING @ SAN FRANCISCO E/S FOUR (4) STOREY TWELVE (12) CLASSROOM, STA. LUCIA H/S FOUR (4) STOREY TWELVE (12) CLASSROOM, ESTEBAN ABADA E/S FOUR (4) STOREY TWENTY (20) SLASSROOM, TORO HILLS E/S FOUR (4) STOREY TWELVE (12)

COMPLETION OF SENIOR HIGH SCHOOL BUILDING @ SAN FRANCISCO E/S FOUR (4) STOREY TWELVE (12) CLASSROOM, STA. LUCIA H/S FOUR (4) STOREY TWELVE (12) CLASSROOM, ESTEBAN ABADA E/S FOUR (4) STOREY TWENTY (20) SLASSROOM, TORO HILLS E/S FOUR (4) STOREY TWELVE (12) is a DPWH-tracked public work in Quezon City 1st DEO, National Capital Region. Reported contract value: ₱9,224,445.20. Status: Reported complete (DPWH). Contractor on record: AYLAN CONST. Figures trace to dpwh.

Quezon City 1st DEO, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation/ Improvement of Flood Control Structures at Baler St. District I, Quezon City
GAA fiscal year
FY2016
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-16-0004539

₱560,000.00 · FY2016

Released to Southern Samar National Comprehensive High ScPS re (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱9,224,445.20

Progress

Reported complete (DPWH)

Start Date

January 17, 2017

Target End

April 16, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.