Buildings and Facilities21O00129

STRUCTURAL IMPROVEMENT OF PUBLIC BUILDINGS AND CONSTRUCTION OF EVACUATION CENTERS AT BOYSTOWN COMPLEX, PARANG, MARIKINA

STRUCTURAL IMPROVEMENT OF PUBLIC BUILDINGS AND CONSTRUCTION OF EVACUATION CENTERS AT BOYSTOWN COMPLEX, PARANG, MARIKINA is a DPWH-tracked public work in National Capital Region, National Capital Region. Reported contract value: ₱92,422,712.73. Status: Past target date (DPWH On-Going). Contractor on record: AYLAN CONST. Figures trace to dpwh.

National Capital Region, National Capital Region
Region: National Capital Region

Follow the peso

2 of 5 steps linked to this project. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    No GAA line found for this project's office and year. The GAA lists budgets by program and office, not always by project.

  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    ₱92,425,900 · AYLAN CONSTRUCTION AND TRADING

    Confirmed (exact contract ID) · score 1.00

    PhilGEPS source ↗
  4. 4. DPWH progress + satellite

    85% reported · imagery 2021-02-02 → 2025-04-25

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: STRUCTURAL IMPROVEMENT OF PUBLIC BUILDINGS AND CONSTRUCTION OF EVACUATION CENTERS AT BOYSTOWN COMPLEX, PARANG, MARIKINA

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2020 GAA. DBM GAA FY2020

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

Confirmed (exact contract ID) · 100%

21O00129

₱92,425,899.92 · AYLAN CONSTRUCTION AND TRADING

Award / contract ref: 21O00129

Contractor

C

127 projects · ₱3.4B total · 0 flags

4. Implementation

Contract Amount

₱92,422,712.73

Progress

Past target date (DPWH On-Going)

Start Date

January 7, 2022

Target End

April 30, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
National Capital Region (NCR)City of MarikinaParang
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
No medium/high hazard on the mapped layers.Details in Hazard context above.Full hazard check →
El Niño outlook (province)
No province on record.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.