Flood Control and Drainage24H00154

REHABILITATION OF FLOOD CONTROL STRUCTURE ALONG NAGHALIN RIVER (UPSTREAM), CATMON, CEBU

REHABILITATION OF FLOOD CONTROL STRUCTURE ALONG NAGHALIN RIVER (UPSTREAM), CATMON, CEBU is a DPWH-tracked public work in Region VII, Region VII. Reported contract value: ₱89,490,419.97. Status: Ongoing (DPWH-reported) (Not Yet Started (DPWH-reported)). Contractor on record: GONZALODO ENT. Figures trace to dpwh.

Region VII, Region VII
Region: Region VII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2023 GAA. DBM GAA FY2023

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

297 projects · ₱8.5B total · 1 flags

4. Implementation

Contract Amount

₱89,490,419.97

Progress

Not Yet Started (DPWH-reported)

Start Date

Data not yet available

Target End

Data not yet available

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.