Roads23DE0093

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, IMPROVEMENT OF ROAD, SAN PASCUAL-SAN JOSE R

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, IMPROVEMENT OF ROAD, SAN PASCUAL-SAN JOSE R is a DPWH-tracked public work in Batangas 2nd DEO, Region IV-A. Reported contract value: ₱120,625,000.00. Status: Reported complete (DPWH). Contractor on record: VICMAR CONST INC 28997. Figures trace to dpwh.

Batangas 2nd DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure at Barangay San Isidro (Section 1), Batangas City
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Batangas 2nd DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

DPWH ID 28997

376 projects · ₱10.1B total · 0 flags

Other projects by this contractor

No sat.

CONSTRUCTION OF UNION - BOTONG - CONSUELO - GENERAL LUNA ROAD, SIARGAO, SURIGAO DEL NORTE

Region XIII, Region XIII

2017₱149.6M
Reported complete (DPWH)
No sat.

IMPRVT./WIDENING OF NAT'L. ROADS, ALLEN-CATARMAN ROAD (S00005SM), KO729+000-KO731+300; KO731+350-KO732+949; KO722+751-KO723+480, NORTHERN SAMAR, 1ST LD

Region VIII, Region VIII

2017₱141.7M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), INTERJURISDICTIONAL ROADS AND/OR BRIDGES (ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS), CONSTRUCTION OF TINGLOY CIRCUMFERENTIAL ROAD - PACKAGE E, SECTION II, TINGLOY, BATANGAS

Batangas 2nd DEO, Region IV-A

2025₱139.2M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), INTERJURISDICTIONAL ROADS AND/OR BRIDGES (ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS), CONSTRUCTION OF TINGLOY CIRCUMFERENTIAL ROAD - PACKAGE E, SECTION I, TINGLOY, BATANGAS

Batangas 2nd DEO, Region IV-A

2025₱139.2M
Past target date (DPWH On-Going)
No sat.

ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEMNETWORK DEVELOPMENT PROGRAM CONSTRUCTION OF BY-PASS AND DIVERSION ROADS ALAMINOS - SAN PABLO CITY BY-PASS ROAD, PACKAGE A, LAGUNA

Region IV-A, Region IV-A

2019₱130.0M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM, REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS, BATANGAS-TABANGAO-LOBO RD - K0138+225 - K0138+302, K0

Batangas 2nd DEO, Region IV-A

2025₱110.4M
Past target date (DPWH On-Going)
View all 376 projects →

4. Implementation

Contract Amount

₱120,625,000.00

Progress

Reported complete (DPWH)

Start Date

April 11, 2023

Target End

August 29, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.