Flood Control and Drainage17FL0054

CONST. OF FLOOD CONTROL AT TONGDOL - GABAO RIVER, IROSIN, SORSOGON, IROSIN, SORSOGON

CONST. OF FLOOD CONTROL AT TONGDOL - GABAO RIVER, IROSIN, SORSOGON, IROSIN, SORSOGON is a DPWH-tracked public work in Sorsogon 2nd DEO, Region V. Reported contract value: ₱47,513,247.15. Status: Reported complete (DPWH). Contractor on record: SUNWEST INC FORMERLY: SUNWEST CONST. Figures trace to dpwh.

Sorsogon 2nd DEO, Region V
Region: Region V

Money Trail

1. Appropriation

Probable match · score 89%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control at Tongdol-Gabao River, Irosin, Sorsogon
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXI-17-0019343

₱311,300.00 · FY2017

Released to Inawayan National Per High School as (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

D

738 projects · ₱73.0B total · 0 flags

4. Implementation

Contract Amount

₱47,513,247.15

Progress

Reported complete (DPWH)

Start Date

June 14, 2017

Target End

December 31, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.