GAA 2025 OO-125DL0132

ASSET PRESERVATION PROGRAM, PREVENTIVE MAINTENANCE - SECONDARY ROADS, MSR JCT-LOPEZ-BUENAVISTA RD - K0218+802-K0219+442, K0219+533-K0220+222, K0220+272-K0220+376, K0220+440-K0221+285, K0221+579-K0222+014, K0222+048-K0222+134

ASSET PRESERVATION PROGRAM, PREVENTIVE MAINTENANCE - SECONDARY ROADS, MSR JCT-LOPEZ-BUENAVISTA RD - K0218+802-K0219+442, K0219+533-K0220+222, K0220+272-K0220+376, K0220+440-K0221+285, K0221+579-K0222+014, K0222+048-K0222+134 is a DPWH-tracked public work in Quezon 4th DEO, Region IV-A. Reported contract value: ₱96,500,000.00. Status: Past target date (DPWH On-Going). Contractor on record: WAYCON BUILDERS AND CONST SUPPLY CORP FOR:WAYCON BUILDERS. Figures trace to dpwh.

Quezon 4th DEO, Region IV-A
Region: Region IV-A

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Camohaguin River, Gumaca, Quezon
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Quezon 4th DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

474 projects · ₱22.2B total · 0 flags

4. Implementation

Contract Amount

₱96,500,000.00

Progress

Past target date (DPWH On-Going)

Start Date

May 16, 2025

Target End

March 11, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.