Roads18KC0032

RECONST. FROM PAVED TO CONCRETE - SAYRE HIGHWAY - K1439+930-K1441+358, K1444+928-K1445+067, K1457+380-K1457+566, K1461+804-K1463+002, K1465+215-K1465+394, K1465+421-K1466+000, K1467+771-K1468+023, MANOLO FORTICH, BUKIDNON

RECONST. FROM PAVED TO CONCRETE - SAYRE HIGHWAY - K1439+930-K1441+358, K1444+928-K1445+067, K1457+380-K1457+566, K1461+804-K1463+002, K1465+215-K1465+394, K1465+421-K1466+000, K1467+771-K1468+023, MANOLO FORTICH, BUKIDNON is a DPWH-tracked public work in Bukidnon 3rd DEO, Region X. Reported contract value: ₱96,500,000.00. Status: Reported complete (DPWH). Contractor on record: M MONTESCLAROS ENT INC. Figures trace to dpwh.

Bukidnon 3rd DEO, Region X
Region: Region X

Money Trail

1. Appropriation

Possible match · score 85%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Flood Control Structure along Sayre Highway with slope protection, Alae-Kisolon Section, Maluko, Manolo Fortich, Bukidnon
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROVIII-18-0005873

₱1,778,742.00 · FY2018

Released to Southern Leyte District Engineering Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱96,500,000.00

Progress

Reported complete (DPWH)

Start Date

March 15, 2018

Target End

December 25, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.