Water Provision and Storage16LH0022

CONSTRUCTION OF WATER SYSTEM AT BRGY. BAGANIHAN, MARILOG DISTRICT, DAVAO CITY

CONSTRUCTION OF WATER SYSTEM AT BRGY. BAGANIHAN, MARILOG DISTRICT, DAVAO CITY is a DPWH-tracked public work in Davao City 2nd DEO, Region XI. Reported contract value: ₱4,900,516.00. Status: Reported complete (DPWH). Contractor on record: FIVE MASSIVE INFRA. Figures trace to dpwh.

Davao City 2nd DEO, Region XI
Region: Region XI

Money Trail

1. Appropriation

GAA FY2016 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

209 projects · ₱1.0B total · 0 flags

4. Implementation

Contract Amount

₱4,900,516.00

Progress

Reported complete (DPWH)

Start Date

March 22, 2016

Target End

September 17, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.