Flood Control and Drainage23AJ0083

CONSTRUCTION OF SLOPE PROTECTION WORKS ALONG SAN JUAN RIVER, PHASE II, SAN JUAN SECTION, SAN CARLOS CITY, PANGASINAN

CONSTRUCTION OF SLOPE PROTECTION WORKS ALONG SAN JUAN RIVER, PHASE II, SAN JUAN SECTION, SAN CARLOS CITY, PANGASINAN is a DPWH-tracked public work in Pangasinan 4th DEO, Region I. Reported contract value: ₱19,364,337.66. Status: Past target date (DPWH On-Going). Contractor on record: 2-R CONST SUPPLY. Figures trace to dpwh.

Pangasinan 4th DEO, Region I
Region: Region I

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Tagamusing River, Sta. 0 + 000 - Sta. 0 + 304, Barangay Tulong, Urdaneta City, Pangasinan
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Pangasinan 4th DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

11 projects · ₱179.8M total · 1 flags

4. Implementation

Contract Amount

₱19,364,337.66

Progress

Past target date (DPWH On-Going)

Start Date

June 21, 2023

Target End

January 26, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.