Construction of Flood Mitigation Structure21PB0004

Construction of Nabuangan River (Upstream) Flood Control, Sta. 37 + 807 - Sta. 38 + 267 (L/S), Sitio Paddig, Brgy. Caglayan, Conner, Apayao

Construction of Nabuangan River (Upstream) Flood Control, Sta. 37 + 807 - Sta. 38 + 267 (L/S), Sitio Paddig, Brgy. Caglayan, Conner, Apayao is a DPWH-tracked public work in APAYAO, Cordillera Administrative Region. Reported contract value: ₱38,292,917.46. Status: Reported complete (DPWH). Contractor on record: ASC CONST & CONCRETE PRODUCTS. Figures trace to sumbong.

APAYAO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Nabuangan River (Upstream) Flood Control, Sta. 37 + 807 - Sta. 38 + 267 (L/S), Sitio Paddig, Brgy. Caglayan, Conner, Apayao
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0012581

₱45,000,000.00 · FY2021

Source

Office-level release, not tied to this specific contract

SARO SARO-CAR-21-0012094

₱322,101.00 · FY2021

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱38,292,917.46

Progress

Reported complete (DPWH)

Start Date

December 2, 2021

Target End

July 12, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.