Buildings and Facilities20DF0193

CONSTRUCTION OF 4STY 8CL SCHOOL BUILDING AT ALAPAN II ELEMENTARY SCHOOL, IMUS CITY, CAVITE

CONSTRUCTION OF 4STY 8CL SCHOOL BUILDING AT ALAPAN II ELEMENTARY SCHOOL, IMUS CITY, CAVITE is a DPWH-tracked public work in Cavite 1st DEO, Region IV-A. Reported contract value: ₱25,000,000.00. Status: Reported complete (DPWH). Contractor on record: FROMARC BUILDERS. Figures trace to dpwh.

Cavite 1st DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

61 projects · ₱1.5B total · 0 flags

Other projects by this contractor

ORGANIZATIONAL OUTCOME 2 : PROTECT LIVES & PROPERTIES AGAINST MAJOR FLOODSFLOOD MANAGEMENT PROGCONST/ REHAB OF FLOOD MITIGATION FACILITIES W/N MAJOR RIVER BASINS AND PRINCIPAL RIVERSCONST OF REVETMENT ALONG ILANG-ILANG RIVER BRGY.ALAPAN SEC PHASE IV

Cavite 1st DEO, Region IV-A

2024₱96.5M
Reported complete (100% progress, DPWH status On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2 : PROTECT LIVES & PROPERTIES AGAINST MAJOR FLOODSFLOOD MANAGEMENT PROGCONST/ REHAB OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS & PRINCIPAL RIVERSCONST OF REVETMENT ALONG JULIAN RIVER, BRGY MALAGASANG I-B, IMUS,

Cavite 1st DEO, Region IV-A

2025₱95.5M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2 :PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODSFLOOD MANAGEMENT PROG CONST/ REHAB OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS & PRINCIPAL RIVERS CONST OF REVETMENT ALONG JULIAN RIVER PHASE 1, BRGY. ANABU I-B IMUS

Cavite 1st DEO, Region IV-A

2025₱95.5M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2 : PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODSFLOOD MANAGEMENT PROGCONST/ REHAB OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS & PRINCIPAL RIVERSCONST OF REVETMENT ALONG JULIAN RIVER, BRGY ANABU I-D, IMUS, CAV

Cavite 1st DEO, Region IV-A

2025₱95.5M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEMNETWORK DEVELOPMENT PROGRAM CONSTRUCTION OF BY-PASS AND DIVERSION ROADSCARSADANG BAGO - MALAGASANG DIVERSION ROAD, ALAPAN - CARSADANG BAGO SECTION, CAVITE

Cavite 1st DEO, Region IV-A

2024₱95.5M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM NETWORK DEVELOPMENT PROGRAMCONSTRUCTION OF BY-PASS AND DIVERSION ROADSCARSADANG BAGO - MALAGASANG DIVERSION ROAD, BUCANDALA SECTION, SEGMENT 2, CAVITE

Cavite 1st DEO, Region IV-A

2024₱77.2M
Reported complete (DPWH)
View all 61 projects →

4. Implementation

Contract Amount

₱25,000,000.00

Progress

Reported complete (DPWH)

Start Date

October 1, 2020

Target End

May 18, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.