Roads19HG0149

LOCAL PROGRAM, LOCAL_ROADS_AND_BRIDGES, LOCAL ROADS, CONSTRUCTION OF CONCRETE ROAD - CONCRETING OF BARANGAY ROAD, MANGACO, GINATILAN, CEBU

LOCAL PROGRAM, LOCAL_ROADS_AND_BRIDGES, LOCAL ROADS, CONSTRUCTION OF CONCRETE ROAD - CONCRETING OF BARANGAY ROAD, MANGACO, GINATILAN, CEBU is a DPWH-tracked public work in Cebu 2nd DEO, Region VII. Reported contract value: ₱6,578,162.00. Status: Reported complete (DPWH). Contractor on record: WORLDWIDE BUILDERS. Figures trace to dpwh.

Cebu 2nd DEO, Region VII
Region: Region VII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

256 projects · ₱2.1B total · 4 flags

Other projects by this contractor

Construction of Dike along Kabalaasnan River, Dumanjug, Cebu

DUMANJUG (CEBU), CEBU, Region VII

2023₱96.5M
Reported complete (DPWH)

Construction of River Retaining Wall Structure at Sitio Upper Talayong, Barangay Tupas, Ronda, Cebu (Upstream)

RONDA (CEBU), CEBU, Region VII

2023₱96.3M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS, FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/ FACILITIES, CONSTRUCTION OF RIVER CHANNEL IMPROVEMENT ALONG SITIO UPPER TALAYONG - SITIO LOWER T

Cebu 7th DEO, Region VII

2023₱75.8M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF SLOPE PROTECTION STRUCTURE - CONSTRUCTION/IMPROVEMENT OF SLOPE PROTECTION/FLOOD MITIGATION STRUCTURE, BARANGAY PANALIPAN, CATMON, CEBU

Cebu 5th DEO, Region VII

2021₱71.3M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF FLOOD CONTROL DIKE AT BARANGAY KABALAASNAN (DOWNST

Cebu 7th DEO, Region VII

2024₱70.9M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF REVETMENT WALL, PUROK LUBE, BARANGAY KABALAASNAN (DOWNSTR

Cebu 7th DEO, Region VII

2025₱70.9M
Past target date (DPWH On-Going)
View all 256 projects →

4. Implementation

Contract Amount

₱6,578,162.00

Progress

Reported complete (DPWH)

Start Date

July 11, 2019

Target End

January 15, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.