Roads16BF0127

ASSET PRESERVATION OF NATIONAL ROADS-PREVENTIVE MAINTENANCE BASED ON PAVEMENT MANAGEMENT SYSTEM/HIGHWAY DEVELOPMENT MANAGEMENT-4(HDM-4)-PRIMARY ALONG SANTIAGO-TUGUEGARAO ROAD (S00760LZ)K0376+000-K0376+178, K0408+500-K0408+598,SAN MANUEL AND QUEZON,ISABELA

ASSET PRESERVATION OF NATIONAL ROADS-PREVENTIVE MAINTENANCE BASED ON PAVEMENT MANAGEMENT SYSTEM/HIGHWAY DEVELOPMENT MANAGEMENT-4(HDM-4)-PRIMARY ALONG SANTIAGO-TUGUEGARAO ROAD (S00760LZ)K0376+000-K0376+178, K0408+500-K0408+598,SAN MANUEL AND QUEZON,ISABELA is a DPWH-tracked public work in Isabela 2nd DEO, Region II. Reported contract value: ₱1,860,494.11. Status: Reported complete (DPWH). Contractor on record: E S PUA CONST. Figures trace to dpwh.

Isabela 2nd DEO, Region II
Region: Region II

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Mallig River Flood Control Project (Barangay San Pedro and Marcos Section), Sta. 0+000 - Sta. 0+750, Roxas, Isabela
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVI-17-0020406

₱-18,489,950.00 · FY2017

Released to Iloilo 4th District Engineering Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

35 projects · ₱119.8M total · 0 flags

4. Implementation

Contract Amount

₱1,860,494.11

Progress

Reported complete (DPWH)

Start Date

February 7, 2017

Target End

March 4, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.