Buildings and Facilities15BF0154

IMPROVEMENT OF BARANGAY ZONE III COMMUNITY CENTER, ZONE III, SAN MARIANO, ISABELA

IMPROVEMENT OF BARANGAY ZONE III COMMUNITY CENTER, ZONE III, SAN MARIANO, ISABELA is a DPWH-tracked public work in Isabela 2nd DEO, Region II. Reported contract value: ₱1,832,379.42. Status: Reported complete (DPWH). Contractor on record: D S T METALCRAFT AND ENGINEERING WORKS. Figures trace to dpwh.

Isabela 2nd DEO, Region II
Region: Region II

Money Trail

1. Appropriation

GAA FY2016 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱1,832,379.42

Progress

Reported complete (DPWH)

Start Date

January 26, 2016

Target End

April 19, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.