Construction of Flood Mitigation Structure24CE0126

Construction of Flood Control Structure along Labong River, Barangay Manacsac, Guimba, Nueva Ecija

Construction of Flood Control Structure along Labong River, Barangay Manacsac, Guimba, Nueva Ecija is a DPWH-tracked public work in GUIMBA (NUEVA ECIJA), NUEVA ECIJA, Region III. Reported contract value: ₱47,762,663.90. Status: Reported complete (DPWH). Contractor on record: NIÑAS CONST CORP FORMERLY: NINA'S CONST AND SUPPLIES. Figures trace to sumbong.

GUIMBA (NUEVA ECIJA), NUEVA ECIJA, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 96%

UACS
18001
Amount
₱25,354,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Casongsong River, Barangay Casongsong, Guimba, Nueva Ecija
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0014806

₱50,000,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0007110

₱2,098,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIII-24-0007111

₱193,000.00 · FY2024

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

135 projects · ₱1.0B total · 3 flags

4. Implementation

Contract Amount

₱47,762,663.90

Progress

Reported complete (DPWH)

Start Date

April 29, 2024

Target End

December 23, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.