Roads24M00178

OFF-CARRIAGEWAY IMPROVEMENT: CONSTRUCTION OF TRAFFIC ISLAND - COTABATO-MARBEL RD - K1714+450 - K1717+050, K1719+800 - K1722+674, BANGA, SOUTH COTABATO

OFF-CARRIAGEWAY IMPROVEMENT: CONSTRUCTION OF TRAFFIC ISLAND - COTABATO-MARBEL RD - K1714+450 - K1717+050, K1719+800 - K1722+674, BANGA, SOUTH COTABATO is a DPWH-tracked public work in Region XII, Region XII. Reported contract value: ₱86,849,261.34. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: ARCINUE COMM'L CORP. Figures trace to dpwh.

Region XII, Region XII
Region: Region XII

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2024 GAA. DBM GAA FY2024

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

118 projects · ₱5.4B total · 3 flags

4. Implementation

Contract Amount

₱86,849,261.34

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

August 12, 2024

Target End

May 29, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.