Roads20FN0072

CONCRETING OF LOCAL ROAD NIÑO JESUS-SABANG-CAWAYAN, STA. MARIA, IRIGA CITYSECTION A: STA. 1+400 STA.1+925.50SECTION B: STA. 2+200 STA. 2+800.00

CONCRETING OF LOCAL ROAD NIÑO JESUS-SABANG-CAWAYAN, STA. MARIA, IRIGA CITYSECTION A: STA. 1+400 STA.1+925.50SECTION B: STA. 2+200 STA. 2+800.00 is a DPWH-tracked public work in Camarines Sur 5th DEO, Region V. Reported contract value: ₱7,682,491.76. Status: Reported complete (DPWH). Contractor on record: S. Figures trace to dpwh.

Camarines Sur 5th DEO, Region V
Region: Region V

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structures along Waras River, Diversion Road - San Antonio - Sta. Lucia, Nabua, Camrines Sur
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Camarines Sur 5th DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

4. Implementation

Contract Amount

₱7,682,491.76

Progress

Reported complete (DPWH)

Start Date

November 24, 2020

Target End

March 1, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.