Buildings and Facilities17HI0059

CONSTRUCTION OF 1 STOREY 2 CLASSROOM SCHOOL BUILDING AT SANTICAN ES, CARMEN, CEBU

CONSTRUCTION OF 1 STOREY 2 CLASSROOM SCHOOL BUILDING AT SANTICAN ES, CARMEN, CEBU is a DPWH-tracked public work in Cebu 5th DEO, Region VII. Reported contract value: ₱2,561,635.82. Status: Reported complete (DPWH). Contractor on record: COCOS TIERRA DEVELOPMENT CORP. Figures trace to dpwh.

Cebu 5th DEO, Region VII
Region: Region VII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of flood control Cebu North Hagnaya Wharf Road, K0039+000-K0039+880, Carmen, Cebu
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-D-17-0022755

₱2,108,129.00 · FY2017

Released to Philippine Air For ( Air Forces ) (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱2,561,635.82

Progress

Reported complete (DPWH)

Start Date

November 2, 2017

Target End

February 24, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.