Buildings and Facilities20CF0140

CONSTRUCTION OF 2STY4CL, TAMBO NORTH E/S, SAN LEONARDO, NUEVA ECIJA

CONSTRUCTION OF 2STY4CL, TAMBO NORTH E/S, SAN LEONARDO, NUEVA ECIJA is a DPWH-tracked public work in Nueva Ecija 2nd DEO, Region III. Reported contract value: ₱8,688,395.88. Status: Reported complete (DPWH). Contractor on record: E D LIBUNAO CONST. Figures trace to dpwh.

Nueva Ecija 2nd DEO, Region III
Region: Region III

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 89%

UACS
18001
Amount
₱45,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Pampanga River Flood Control, Tambo Adorable, San Leonardo, Nueva Ecija
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Nueva Ecija 2nd DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

4. Implementation

Contract Amount

₱8,688,395.88

Progress

Reported complete (DPWH)

Start Date

August 25, 2020

Target End

December 22, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.