Flood Control and Drainage20KD0047

CONST OF FLOOD CONTROL STRUCTURE, UPSTREAM OF BCIR ALONG PUERTO RIVER, BOTH SIDES, PUERTO, CDOC

CONST OF FLOOD CONTROL STRUCTURE, UPSTREAM OF BCIR ALONG PUERTO RIVER, BOTH SIDES, PUERTO, CDOC is a DPWH-tracked public work in Cagayan de Oro City 2nd DEO, Region X. Reported contract value: ₱48,528,739.02. Status: Reported complete (DPWH). Contractor on record: EQUI-PARCO CONST CO. Figures trace to dpwh.

Cagayan de Oro City 2nd DEO, Region X
Region: Region X

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱46,930,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure Upstream of BCIR along Dansoli and Gusa Creeks, Both Sides, Gusa, Cagayan de Oro City
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Cagayan de Oro City 2nd DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

725 projects · ₱77.9B total · 5 flags

4. Implementation

Contract Amount

₱48,528,739.02

Progress

Reported complete (DPWH)

Start Date

March 9, 2020

Target End

November 17, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.