Construction of Flood Mitigation Structure24IL0022

Construction of Caaga - San Jose Flood Control Structure, Malitbog, Southern Leyte

Construction of Caaga - San Jose Flood Control Structure, Malitbog, Southern Leyte is a DPWH-tracked public work in MALITBOG (SOUTHERN LEYTE), SOUTHERN LEYTE, Region VIII. Reported contract value: ₱49,000,000.00. Status: Reported complete (DPWH). Contractor on record: JDR CONST / JGO BUILDERS. Figures trace to sumbong.

MALITBOG (SOUTHERN LEYTE), SOUTHERN LEYTE, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Caaga - San Jose Flood Control Structure, Malitbog, Southern Leyte
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-24-0008706

₱1,921,000.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-24-0002533

₱344,163.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-24-0008707

₱177,000.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-24-0006505

₱132,887.00 · FY2024

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

1 projects · ₱49.0M total · 0 flags

4. Implementation

Contract Amount

₱49,000,000.00

Progress

Reported complete (DPWH)

Start Date

February 13, 2024

Target End

October 31, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.