Roads18L00185

CONST. OF CONCRETE ROAD-MONTEVISTA-DNAS ROAD (DNAS-LAAK), PACKAGE 2 INCLUDING ROW, COMPOSTELA VALLEY

CONST. OF CONCRETE ROAD-MONTEVISTA-DNAS ROAD (DNAS-LAAK), PACKAGE 2 INCLUDING ROW, COMPOSTELA VALLEY is a DPWH-tracked public work in Region XI, Region XI. Reported contract value: ₱279,257,258.61. Status: Reported complete (DPWH). Contractor on record: ULTICON BUILDERS INC. Figures trace to dpwh.

Region XI, Region XI
Region: Region XI

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

GAA FY2018 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱279,257,258.61

Progress

Reported complete (DPWH)

Start Date

January 28, 2020

Target End

January 18, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.