Buildings and Facilities20EI0181

CONSTRUCTION OF EVACUATION CENTER, BARANGAY POBLACION, BULALACAO, ORIENTAL MINDORO

CONSTRUCTION OF EVACUATION CENTER, BARANGAY POBLACION, BULALACAO, ORIENTAL MINDORO is a DPWH-tracked public work in Southern Mindoro DEO, Region IV-B. Reported contract value: ₱34,739,949.20. Status: Reported complete (DPWH). Contractor on record: A D L CONSTRAK OPC FORMERLY: A D L CONSTRAK. Figures trace to dpwh.

Southern Mindoro DEO, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱34,739,949.20

Progress

Reported complete (DPWH)

Start Date

August 30, 2020

Target End

December 31, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.