Roads25CL0183

CONCRETING OF BANTAY CARMEN TO SAGPAT FMR, BRGY. MALOMA, SAN FELIPE, ZAMBALES

CONCRETING OF BANTAY CARMEN TO SAGPAT FMR, BRGY. MALOMA, SAN FELIPE, ZAMBALES is a DPWH-tracked public work in Zambales 1st DEO, Region III. Reported contract value: ₱49,053,437.76. Status: Past target date (DPWH On-Going). Contractor on record: RAIK CONST AND DEVELOPMENT CORP FORMERLY: RAIK CONST AND SUPPLY. Figures trace to dpwh.

Zambales 1st DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Stabilization Structure along Gabor River, Phase 1, San Felipe, Zambales
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Zambales 1st DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

4. Implementation

Contract Amount

₱49,053,437.76

Progress

Past target date (DPWH On-Going)

Start Date

April 3, 2025

Target End

November 8, 2025

5. Audit