Flood Control and Drainage25DQ0088

CONSTRUCTION OF SLOPE PROTECTION WORKS ALONG CARMONA RIVER, PHASE 1, GEN. MARIANO ALVAREZ, CAVITE

CONSTRUCTION OF SLOPE PROTECTION WORKS ALONG CARMONA RIVER, PHASE 1, GEN. MARIANO ALVAREZ, CAVITE is a DPWH-tracked public work in Cavite 3rd DEO, Region IV-A. Reported contract value: ₱94,762,977.55. Status: Past target date (DPWH On-Going). Contractor on record: OMNICON BUILDERS. Figures trace to dpwh.

Cavite 3rd DEO, Region IV-A
Region: Region IV-A

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Slope Protection and Flood Protection Structure along Carmona River, Phase 2, Carmona, Cavite
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Cavite 3rd DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

4. Implementation

Contract Amount

₱94,762,977.55

Progress

Past target date (DPWH On-Going)

Start Date

April 16, 2025

Target End

March 14, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.