Roads20DG0007

ROAD WIDENING-ALONG INDANG-ALFONSO VIA LUKSUHIN RD. (SO5882LZ) K0072+306-K0072+338,K0072+353-K0072+4

ROAD WIDENING-ALONG INDANG-ALFONSO VIA LUKSUHIN RD. (SO5882LZ) K0072+306-K0072+338,K0072+353-K0072+4 is a DPWH-tracked public work in Cavite 2nd DEO, Region IV-A. Reported contract value: ₱11,779,191.98. Status: Reported complete (DPWH). Contractor on record: TJMT CONST. Figures trace to dpwh.

Cavite 2nd DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 71%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structures/Facilities along Libmanan River at Brgy. Sibujo, Libmanan, Camarines Sur
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Cavite 2nd DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

227 projects · ₱6.0B total · 35 flags

Other projects by this contractor

No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - PRIMARY ROADS MAHARLIKA HIGHWAY (CAGAYAN VALLEY ROAD) - K0541+000 - K0541+533, K0548+000 - K0548+920, K0549+050 - K0549+940, K0550+094 - K0550+605.50

Region II, Region II

2025₱138.5M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - CONSTRUCTION OF CONCRETE ROAD - GATTARAN DIVERSION ROAD, PACKAGE 1, GATTARAN, CAGAYAN

Cagayan 1st DEO, Region II

2025₱135.1M
Past target date (DPWH On-Going)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: BRIDGE - BRIDGE PROGRAM - REPLACEMENT OF PERMANENT WEAK BRIDGES - NAGANTATAPIAN BRIDGE (B01094LZ) ALONG CAGAYAN VALLEY ROAD

Region II, Region II

2023₱119.7M
Past target date (DPWH On-Going)
No sat.

OO1: ENSURE SAFE & RELIABLE NATL RD SYSTEM - ASSET PRESERVATN - REHAB/ RECONST/ UPGRADING OF DAMAGED PAVED RDS - TERTIARY ROADS - REHABILITATION OF PAVED ROAD - BBDSMR- K0519+331-K0519+600.50 TO K0546+000-K0547+1012.5, BAGGAO, CAGAYAN

Cagayan 1st DEO, Region II

2024₱102.4M
Past target date (DPWH On-Going)
No sat.

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEM - CONSTRUCTION OF SEAWALL, BARANGAY PADDAYA, APARRI, CAGAYAN

Cagayan 1st DEO, Region II

2025₱96.5M
Past target date (DPWH On-Going)

Construction of Flood Control Structure along Cagayan River, Aguigican, Gattaran, Cagayan, Package 1

GATTARAN (CAGAYAN), CAGAYAN, Region II

2024₱96.5M
Reported complete (DPWH)
View all 227 projects →

4. Implementation

Contract Amount

₱11,779,191.98

Progress

Reported complete (DPWH)

Start Date

June 30, 2020

Target End

October 27, 2020

5. Audit